Mississippi River Bridge

Developing: Mississippi River Bridge
11:35 am
Wed March 28, 2012

Updated reports: Worker falls into river at Mississippi River Bridge construction site

A view of the Mississippi River Bridge construction area from a time-lapse camera taken at 11 a.m. today.
(Missouri Department of Transportation website)

Updated at 10:05 p.m.

The St. Louis Post-Dispatch, quoting East St. Louis Police chief Michael Floore, says the missing worker has tentatively been identified as 35-year-old Andy Gammon of Park Hills, Mo., which is about 65 miles south of St. Louis. The Post-Dispatch says investigators from the Occupational Safety and Health Administration are on scene to investigate.

Read more
Mississippi River Bridge
5:22 pm
Tue November 29, 2011

Metro East Black Contractors file racial discrimination suit against IDOT

The Mississippi River Bridge under construction. The Metro East Black Contractors Organization is suing the Illinois Department of Transportation for racial discrimination.
(via Missouri Department of Transportation)

The new Mississippi Bridge Project  is facing a new obstacle. The Metro East Black Contractors Organization is suing to stop the Illinois Department of Transportation from handing out more contracts on the $760 million project until discrimination issues are addressed.

The organization says they aren't getting their fair share of work on the project. The group's attorney Eric Vickers says in addition to an injunction on awarding more contracts, the new lawsuit calls for IDOT to pay $650 million in damages.

Read more
Morning Round-up
9:41 am
Mon October 10, 2011

Morning headlines: Monday, October 10, 2011

The St. Louis Cardinals lost game 1 of the National League Championship Series at Miller Stadium in Milwaukee, Wisc.
(via Flickr/ConspiracyofHappiness)

Cardinals lose Game 1 of NLCS

Read more
I-70 Closure Downtown This Weekend
1:32 pm
Wed October 5, 2011

All-lane closure of I-70 in downtown St. Louis Oct. 6-12

View I-70 Downtown Closure - Oct. 6-12 2011 in a larger map

A map of the closure area can be seen above.

Heading to the Roger Daltry concert at the Peabody or the Blues' opening game this weekend? Or were you thinking of cruising around downtown for any other reason from Oct. 6-12? Well, if your travel plans include using Interstate 70 between 10th St. and the Poplar Street Bridge, we offer the friendly suggestion to find an alternate route.

Read more
I-70 ramp closure
12:41 pm
Wed September 28, 2011

MoDOT permanently closes I-70 ramp to 10th Street Oct. 10

Mississippi River Bridge under construction.
(Courtesy of MoDOT)

The Missouri Department of Transportation and its contractor Millstone Bangert Inc. will permanently close the exit ramp 249A from eastbound Interstate 70 to 10th Street in St. Louis City at  9  a.m. October 10, 2011.

The ramp will be removed permanently so crews can construct roadway and ramps between I-70 and the new Mississippi River Bridge. The new ramps to the bridge will cross directly over the current location of the 10th Street exit ramps.

Drivers can use Broadway exit 250A to get into the city.

Read more
Morning round-up
9:25 am
Wed August 3, 2011

Morning headlines: Wednesday, August 3, 2011

Mississippi River Bridge under construction.
Photo courtesy of MoDOT

Workers threaten to shut down construction on Mississippi River bridge

A group that's trying to get more construction jobs for minority workers says it'll shut down work on a new Mississippi River bridge near St. Louis. The Metro East Black Contractors Organization says it's meeting with the director of the Illinois Department of Transportation on Friday. The group says it'll shut down work on Monday if the meeting isn't satisfactory.

St. Louis Science Center to reduce number of VPs

Read more
New river bridge
4:11 pm
Tue June 28, 2011

High water slowing work on new Mississippi River Bridge

Work continues on the piers for the new Mississippi River Bridge just north of downtown, though high water is making things less efficient.
(photo courtesy of MoDOT)

The moderate flooding along the Mississippi River at St. Louis is costing crews building the piers for the new bridge a couple of days of work a week.

MoDOT project manager Greg Horn said workers are still out on the piers six days a week, 20 hours a day. But the flooding - the river is about five feet above flood stage - means crews can only work at about 60 percent efficiency.

Read more
MoDOT Construction Updates
5:30 pm
Wed February 23, 2011

MoDOT updates on Poplar St. Bridge, I-64 construction

Officials with the Missouri Department of Transportation say work on the Poplar Street Bridge will start this spring and continue into the fall.

The work will involve resurfacing the bridge deck and will result in lane closures and traffic delays.

Deanna Venker is an area engineer for MoDOT.  She says the work could not be delayed until the completion of the new Mississippi River bridge in 2014.

Read more
New bridge
2:17 pm
Wed December 29, 2010

Miss. River Bridge gets back on schedule

The site of the new Mississippi River Bridge at the foot of Mullanphy St. in north St. Louis.
(Rachel Lippmann, St. Louis Public Radio)

Crews working on the new Mississippi River Bridge have gotten the $640 million project back on track.

Flooding meant that for the months of May, June, and July, it wasn't safe for crews to be working below the water line, says project manager Greg Horn. That wiped out 81 construction days.

Read more