Bill Laskowsky (left) and Darryl Piggee, representatives of the Northside Regeneration urgent care project, show renderings for the proposal.
Kae Petrin | St. Louis Public Radio

An aldermanic committee voted Wednesday to extend deadlines and renew tax incentives for the developers behind Northside Regeneration’s slow-moving urgent care project. 

The vote came after the city's own attorney and its economic development arm pointed out legal and financial concerns.

Site of the Northside Regeneration Urgent Care, pictured in September 2019.
Kae Petrin | St. Louis Public Radio

The St. Louis Board of Aldermen will consider renewing a development agreement for Northside Regeneration’s long-stalled urgent care center, even as the developer and the city continue to tangle in court over the larger development project.

The bill would give Paul McKee a two-year extension to secure financing and build the facility, which would be located on Jefferson Avenue on the former Pruitt-Igoe site. The bill, introduced Friday by Alderwoman Tammika Hubbard, D-5th Ward, would also requalify the project for more than $8 million in tax incentives. 

A partially built wall at the Northside Regeneration urgent care project collapsed last year after high winds. Pictured on December 28, 2018.
File Photo | Kae Petrin | St. Louis Public Radio

Updated 2 p.m., March 30, with comment from Paul McKee's spokesperson — The design builder for developer Paul McKee's planned urgent care facility has asked the City of St. Louis to reinstate its building permits, according to a press release sent Saturday by a McKee spokesperson.

Delays at the construction site, which the city had marked "abandoned," were caused by the federal government shutdown, which delayed the issuance of tax credits, according to the statement. Design builder KAI plans to resume construction at the site by June, according to the statement.

Original story from March 26: 

A three-bed urgent-care hospital planned by developer Paul McKee has lost its city building permits.

In December, after months of inactivity at the site, the project’s partial walls collapsed. Last month, the city marked the site as “abandoned” after little communication from the contractor, St. Louis Building Commissioner Frank Oswald said.

(courtesy M Properties)

Northside Regeneration’s plans for the old Pruitt-Igoe site became public this week, including a $72 million complex of medical buildings, commercial and office space and two hotels.

Developer Paul McKee’s company bought the 34-acre site from the city for $1 million last summer. Northside Regeneration had held the option for several years, and McKee previously received state approval to build a three-bed urgent care facility within the former federal housing site.

Marshall Griffin/St. Louis Public Radio

The long-delayed NorthSide Redevelopment project in St. Louis took a step forward Monday.

The Missouri Department of Health's Facilities Review Committee granted a certificate of need for a three-bed urgent care hospital that's part of developer Paul McKee's master plan for the overall project.  No one spoke in opposition to granting McKee a certificate of need during the committee's meeting, and the vote in favor was 7-0.

The facility is to be built at 25th Street and Maiden Lane.

Developer Paul McKee outlined his plans for an urgent care hospital at 25th St. and Maiden Ln. in July of 2014.
Maria Altman | St. Louis Public Radio

Developer Paul McKee unveiled plans Wednesday for an urgent care facility on the north side of St. Louis, but questions at the press event turned to the lack of infrastructure projects in McKee's massive, 1,500 acre redevelopment area.